Pre-Shipment Inspection in Pakistan: The Complete Buyer's Guide

Pre-shipment inspection in Pakistan: AQL sample sizes and accept limits, a worked example, the booking checklist and what a report needs to hold up in a claim.

Line drawing of packed cartons, one opened for a random sample, and a ticked checklist, labelled Packed lot

Pre-shipment inspection is a random-sample check of a finished, packed order against the purchase order, made before the container is loaded. The lot size fixes how many pieces the inspector opens, and the agreed AQL fixes how many defects the lot may carry and still pass. The verdict is arithmetic, not opinion.

Book it for the day the last carton is packed, with enough days before the vessel cut-off to rework a failed lot and inspect it again. An inspection with no time left behind it can only record a problem, not fix it.

What a pre-shipment inspection checks

An inspector attends the factory or warehouse, confirms the lot is the one on the purchase order, draws a random sample of cartons and pieces, and checks them against the specification both sides signed. The scope follows the order, but most programmes cover the same six things:

  • Quantity and assortment: pieces, sizes and colours packed against the order.

  • Workmanship: every visible defect in the sample, logged and classed as critical, major or minor.

  • Measurements: key points measured against the size chart and its tolerances.

  • On-site tests named in the order, such as a zip run, a seam pull or a barcode scan.

  • Labels and marking: care, content and origin labels, swing tags and carton marks.

  • Packing: carton count, carton condition, packing method and the packing list.

Two limits are worth stating plainly. An inspection is not certification: it reports on the lot presented on the day. And it is not a laboratory test: fibre content, colour fastness and restricted substances need analytical testing.

Timing differs by provider. Tti Inspections books pre-shipment inspection at the 100 percent packed stage, so every carton that will ship is in the population the sample is drawn from. Some providers start once 80 percent of the order is complete or export-packed (QIMA, Cotecna). That is faster, but the last fifth of the order is never in the sample.

How AQL sampling turns a lot into pass or fail

Three inputs decide the verdict. The lot size gives a code letter and a sample size. The inspection level adjusts that sample, and general level II is the default when nothing else is agreed. The acceptable quality limit (AQL), set separately for each defect class, gives the accept and reject numbers. The tables come from ANSI/ASQ Z1.4 and its international counterpart, ISO 2859-1.

The table below covers the lot sizes most apparel and home textile orders fall into, with the two AQLs buyers use most: 2.5 for major defects and 4.0 for minor ones.

Lot size (pieces)

Code letter

Sample size

Major, AQL 2.5: accept / reject

Minor, AQL 4.0: accept / reject

281 to 500

H

50

3 / 4

5 / 6

501 to 1,200

J

80

5 / 6

7 / 8

1,201 to 3,200

K

125

7 / 8

10 / 11

3,201 to 10,000

L

200

10 / 11

14 / 15

10,001 to 35,000

M

315

14 / 15

21 / 22

Critical defects are the ones that could injure the user or break a legal requirement, such as a broken needle left in a garment or a small part that can come off a child's item. Most buyers accept none: a single critical defect in the sample fails the lot, whatever the major and minor counts show.

The sample does not grow in step with the lot. A lot 300 times bigger gets a sample only 10 times bigger, so the share of the order opened falls from about 4 percent at 3,000 pieces to about 1 percent at 30,000.

Bar chart of how many pieces an inspector samples at general inspection level II as the lot grows: 50 pieces for lots of 281 to 500, 80 for 501 to 1,200, 125 for 1,201 to 3,200, 200 for 3,201 to 10,000, 315 for 10,001 to 35,000 and 500 for 35,001 to 150,000. A lot 300 times bigger gets a sample only 10 times bigger.

That is why the AQL matters more on big lots. On a 30,000-piece order at AQL 2.5, 14 major defects in a 315-piece sample still pass.

A worked example: 3,000 polo shirts

A buyer orders 3,000 polo shirts with critical 0, major 2.5 and minor 4.0 at general level II. The lot is code K, so the inspector opens 125 pieces drawn from cartons across the whole lot.

  • Critical: none found. Passes.

  • Major: 6 found, against an accept number of 7. Passes.

  • Minor: 12 found, against a reject number of 11. Fails.

The lot fails on minor defects even though the major count passed, because each class is judged on its own. The usual next step is a sort and rework of the whole lot by the factory, then a re-inspection of a fresh sample at the same plan.

Switching rules: when the plan should tighten or relax

AQL plans are built for a run of lots from one supplier, not a single order. ISO 2859-1 sets three severities and the rules for moving between them:

  • Normal to tightened: 2 lots out of 5 or fewer consecutive lots are not accepted on first inspection.

  • Tightened back to normal: 5 consecutive lots are accepted.

  • Normal to reduced: production is steady, the supplier has built up a strong run of accepted lots measured by the standard's switching score, and the responsible authority, usually the buyer, agrees.

  • Reduced back to normal: any lot is not accepted, or production becomes irregular.

Tightened inspection uses stricter accept numbers, so a supplier with a poor record has to deliver better lots to pass. Writing the switching rules into the inspection protocol costs nothing and puts the pressure where the record says it belongs.

Book it so a failed lot can still be fixed

Count back from the vessel cut-off, not forward from the end of production. The plan needs the inspection day, the report, a rework window and a re-inspection, and only then loading. Tti Inspections confirms bookings within 24 hours and issues the report within 24 hours of the inspection finishing, which keeps the rework window as long as the production schedule allows.

Send these with the booking request, so the inspector checks the order the buyer placed and not the one the factory remembers:

  • Purchase order with quantities by style, colour and size.

  • Approved sample or its reference, and any comments from sample approval.

  • Specification and size chart with tolerances.

  • Defect list classed as critical, major and minor.

  • AQL for each class and the inspection level.

  • On-site tests to perform and how each is passed.

  • Label and carton-mark artwork, and the packing list.

  • Factory address, contact person and the planned ex-factory date.

What a report needs to hold up in a claim

The report is the product. If a dispute reaches a claim, it is the only record of what was in the cartons, so it has to let a third party repeat the decision.

  • Lot identity: order number, styles, quantity presented and the carton numbers opened.

  • Sampling basis: lot size, code letter, sample size, and the AQL and accept and reject numbers for each class.

  • Defect log by class, with a photograph of each defect type.

  • Measurements recorded against the tolerance, not just marked pass or fail.

  • Quantity, assortment and carton counts against the packing list.

  • Packing, labelling and carton condition, with photographs.

  • The verdict with its arithmetic: PASS, FAIL or HOLD, and the count that decided it.

Pre-shipment inspection is one of eight stages

A final check finds problems when they are most expensive to fix. Tti Inspections runs eight stages for softlines, and a programme can use as many as the risk justifies: sample picking at about 10 percent of production, pre-production inspection before manufacturing begins, initial production inspection at about 10 to 20 percent, during-production inspection at about 30 to 60 percent, pre-final inspection at about 60 to 80 percent, pre-shipment inspection at 100 percent packed, a full check of every piece where the risk demands it, and loading supervision at the container.

Pre-shipment inspection is one of eight stages in the inspection cycle

Each stage answers a question the next cannot. Whether the fabric is right is answerable before cutting and too late at packing. Whether the right cartons went into the container is answerable only at loading.

What Tti Labs covers

Tti Labs' inspection arm, Tti Inspections Pvt Ltd, is accredited to ISO/IEC 17020 by the Pakistan National Accreditation Council under certificate IB-006, valid to 12 Sep 2027 and listed on the PNAC active register.

  • Pre-shipment inspection against the purchase order, sampled to ANSI/ASQ Z1.4, with default limits of critical 0, major 2.5 and minor 4.0 at general level II unless the buyer sets others.

  • Four-point fabric grading to ASTM D5430 where fabric is in scope.

  • All eight softlines stages, so a programme can be built around the production moments that carry the risk.

  • Laboratory follow-up under ISO/IEC 17025, PNAC accreditation LAB-022, when a defect raises a material question.

  • Offices in Lahore, Karachi, Faisalabad and Sialkot.

  • Booking confirmed within 24 hours and the report within 24 hours of the inspection.

Tti Labs reports what it finds on the goods presented. A report does not certify the supplier's management system or guarantee that later production will match the lot inspected.

Book a pre-shipment inspection with Tti Inspections Pvt Ltd. UAN 111 786 001. Reports built to hold up in a claim.

Related guides: AQL Inspection in Pakistan: Sample Sizes, Accept and Reject Limits, Third-Party Inspection in Pakistan: How Independent QC Actually Works, Factory Audit in Pakistan: The Supplier Checklist Buyers Should Require, Denim QC in Pakistan: Shade, Wash and Measurement.

FAQ

What is pre-shipment inspection in Pakistan?

A random-sample check of a finished, packed order against the purchase order, made at the factory or warehouse before the container is loaded. AQL sampling tables decide whether the lot passes.

How many pieces does a pre-shipment inspection check?

It depends on the lot size. At general inspection level II, a lot of 1,201 to 3,200 pieces gets a 125-piece sample, a lot of 3,201 to 10,000 gets 200, and a lot of 10,001 to 35,000 gets 315.

How is AQL applied to apparel lots?

The buyer sets an AQL for each defect class, commonly 0 for critical, 2.5 for major and 4.0 for minor. Each class has its own accept and reject numbers for the sample size, and the lot fails if any class reaches its reject number.

When should a buyer book pre-shipment inspection before ETD?

For the day the order is fully packed, with enough time before the vessel cut-off for a rework and a re-inspection if the lot fails. Tti Inspections confirms bookings within 24 hours and reports within 24 hours of the inspection.

What happens if a lot fails pre-shipment inspection?

The factory usually sorts and reworks the whole lot, then a fresh sample is inspected at the same plan. Repeated failures should move the supplier to tightened inspection under the ISO 2859-1 switching rules.

References

  1. Sampling procedures for inspection by attributes, Part 1 (IS 2500-1:2000, identical to ISO 2859-1:1999), Bureau of Indian Standards, https://archive.org/download/gov.in.is.2500.1.2000/is.2500.1.2000.pdf

  2. Pre-shipment inspection, QIMA, https://www.qima.com/consumer-products/pre-shipment-inspection

  3. Consumer products inspection, Cotecna, https://www.cotecna.com/en/services/consumer-products/inspection

  4. Inspection services, Tti Labs, https://www.ttilabs.net/inspection

  5. Analytical testing services, Tti Labs, https://www.ttilabs.net/testing

  6. Active inspection bodies register, Pakistan National Accreditation Council, https://www.pnac.gov.pk/index.php/Accredited-Cabs-serve/Inspection-Bodies/Active

  7. Accreditation scope LAB-022 (ISO/IEC 17025:2017, valid to 8 Aug 2027), Pakistan National Accreditation Council, https://pnac.gov.pk/pdfFiles/LAB-022

  8. Contact, Tti Labs, https://www.ttilabs.net/contact

Keep Reading

More insights on testing, compliance, and sustainability from Tti Labs

Different packaging materials, a cardboard box, a recyclable pouch and molded pulp tray, on a white surface

General

PPWR packaging rules for Pakistan exporters: recyclable design, recycled content targets, empty space limits and why the EPR fee falls on the EU importer.

Line drawing of a marked fabric specimen, a washer and the smaller specimen after washing, labelled After wash

General

Fabric shrinkage testing explained: ISO 5077, ISO 6330 and AATCC 135 and 150, how the percentage is calculated, spirality, and how to set the limit.

Line drawing of a product label naming the factory and the EU contact, linked to both, labelled EU contact

General

What the EU GPSR asks of Pakistani exporters: the EU responsible person, labels, technical documentation, online listings, and the tests that back them.